WORK ORDERSWO-2026-0460
WO-2026-0460OpenMediumPreventive
LT-003 — Generac MLT6SMD Light Tower
Created 2026-05-13 · Assigned to M. Thompson
JOB DESCRIPTION
Quarterly PM — auto-generated from PM schedule PM-002. Due: 2026-05-15
PM CHECKLIST — Light Tower — Monthly Inspection
Test mast raise/lower operation — full cycle
Inspect all bulbs/LEDs for function
Check ballast operation and connections
Check engine oil level
Verify fuel level and cap seal
Check tire pressure — all four tires
Inspect stabilizer legs for damage
Check wiring and connections for chafing
Test emergency stop functionCRITICAL
Inspect tow hitch, coupler, and safety chains
Complete all 10 items to submit
Cost Breakdown
Regular Labour (0.00h × $95/h)$0.00
OT Labour (0.00h × $143/h)$0.00
Parts & Materials$0.00
TOTAL$0.00
Complete the WO to record labour and finalize cost
Parts & Materials
0 itemsNO PARTS LOGGED YET
Related Service History
Note2026-05-13· M. Thompson
Work order WO-2026-0460 created — Quarterly PM — auto-generated from PM schedule PM-002. Due: 2026-05-15
📷
Before / After / DamageWork Order Photos
Photos are attached to this work order and included in the submission package. Tap a photo to add a caption describing what you found.